Applicant: DAR Construction
Prospective Buyer: Scott Turner
Proposal: Total demolition. Developer is looking to tear down existing structure to build two units.
Mar 5th, 2025: Developer scheduled wtih Historic Landmark Commission to request demolition permit. OWANA believes this will again be postponed until developer meets with Architectural Review Committee.
Feb 27th, 2025: Developer met with OWANA. OWANA suggested postponing until developer meets with Architectural Review Committee.
Feb 12th, 2025: Developer fails to appear at Architectural Review Committee.
Feb 5th, 2025: Developer attends Historic Landmark Commission to request demolition permit to tear down the structure. OWANA presents an alternative site plan with the first 15ft of the structure remaining intact. Historic Landmark Commission postpons a decision pending the developer meeting with the Architectural Review Committee to explore this option.
Jan 2025: Developer met with OWANA to present proposal to tear down the existing structure and building two units in its place. OWANA requests keeping the first 15ft of the exising structure to maintain neighborhood character.